LSU Temporary University Hospital Level One Trauma Center

LSU Temporary University Hospital Level One Trauma Center

Commercial

All Star Electric, Inc. completed a $9.5 million electrical installation as part of the repairs and renovation of this vital downtown medical center after Hurricane Katrina. Our work was divided into two phases, with each planned and executed along a fasttrack, 120-day schedule in order to help restore the continuum of health services in New Orleans as soon as possible. The project was completed in 2007.

Architect: Blitch Knevel Architects, New Orleans, La
Engineer: URS, New Orleans, La
Phase I General Contractor: Landis Construction Co., LLC
Phase II General Contractor: The McDonnel Group

Status: Completed