The first phase of the project consisted of relocation of the press box/press area from the 300 level to the 700 level, as well as the build out of 13 new luxury suites on the 300 level. The locker room was completely gutted and rebuilt into a state-of-the-art facility for the Saints. The second phase consisted of a total remake of the 100 plaza level, including concession areas and bathrooms. The 100 level seating along the sidelines were removed and replaced with permanent seating. Under the new permanent seating, All-Star installed two new floor level Bunker Clubs, which are used to entertain fans during the pregame festivities.

Status: Completed